Consider both demand and forecast orders for scheduling.

APS

Requirement

  • Consider both demand and forecast orders for scheduling.
  • Use moulds for a specific number of days to achieve usage cycle.
  • Use specific machines for product lines.
  • Split orders between plants to meet market demand.

Objectives

  • Minimize setup time to have effective scheduling.
  • Split orders by product type between plants.
  • Maximize mould usage.

Present State

  • Built different configs for forecast and actual demand.
  • Used Preactor AP to derive MPS to split orders.
  • Used inbuilt Preactor capability [Secondary Constraints and required resource] to schedule on specific machines.
  • Used Secondary constraints to achieve required mould cycle to minimize setup.
Other Case Studies

Looking to start your digital success story?

Explore how our solutions can bring real benefits to your operations.
Get in touch with us by filling out the form and our team will contact you.

look